VT-GHI β€” Unscheduled: Cargo Door Latch

PRJ-2026-003 Β· VT-GHI Β· Boeing 737-800 Β· PM Ananya Rao

Progress

0%

Planned Start / Completion

2026-03-18 β†’ 2026-03-24

Actual Start / Completion

Not started β†’ In progress

Lead Technician

Arjun Nair

Project Type

UNSCHEDULED

AI Maintenance Insight β€” Prototype

VT-GHI β€” Unscheduled: Cargo Door Latch is currently 8% behind the planned schedule.

Potential contributors:

  • Replacement latch mechanism (part-6) is awaiting receipt β€” may delay start.

Recommended action: Prioritize outstanding work orders and any pending compliance review.

Work Packages

Cargo Systems ATA 52

NOT STARTED

Cargo door and latch mechanism inspection tasks.

0% Β· due 2026-03-24

Technician: Arjun Nair Β· Inspector: Not yet assigned Β· Ref: AD-2026-005

Work Orders

View all β†’
WO#TaskATAPriorityTechnicianDueStatus
WO-1046Cargo Door Latch Mechanism Inspection52HIGHArjun Nair2026-03-22ASSIGNED

Assigned Technicians

Parts

  • LATCH-778AWAITING RECEIPT

Defects

No defects reported for this project’s work orders.

    Compliance

    Evidence

    Structured Record ReferenceVerified

    Aircraft Master Record β€” ac-7

    Aircraft configuration record supporting the applicability determination.

    Structured Record Reference12/21/2025, 8:00:00 AM

    Related to 1 condition

    Activity / Audit

    No audit events recorded yet.